A company's procurement team is negotiating a three-year contract to build a new manufacturing facility. Management asks the internal auditor which contract type will most clearly transfer the risk of cost overruns to the contractor. Which contract type is most appropriate if the organization wants to minimize its exposure to unexpected increases in total project cost?
Show the answer and explanation
Correct answer: A. Enter into a fixed-price contract with the contractor that specifies a set total price for the work
A fixed-price contract places responsibility for cost overruns on the contractor because the contractor agrees to deliver the specified scope for a set total price; therefore the buyer's exposure to unexpected increases is minimized. A cost-plus contract reimburses actual costs plus a fee, so the buyer bears cost escalation risk. A time-and-materials contract similarly reimburses actual labor and materials as incurred, leaving cost uncertainty with the buyer. A unit-price contract shifts some pricing risk but still leaves quantity and scope risk with the buyer—if quantities exceed estimates the buyer can face higher total costs—so it does not transfer risk as clearly as a fixed-price agreement.
Want more practice?
Prepare for the Certified Internal Auditor (CIA) exam with CIA 2026 – Certified Internal Auditor Exam Preparation (Parts 1, 2 & 3) – Training Program.